PROJECT OVERVIEW
About This Project
This project encompassed the development of design plans, specifications, quantity take-offs, and a detailed construction cost estimate for the resurfacing and ADA improvements along US 34 (Ogden Ave.), spanning from Raymond Drive/Aurora Avenue to just west of I-355. The total length of the project corridor was approximately 36,960 feet (7 miles), and construction activities were carried out using intermittent or moving operations to minimize traffic disruption.
The project primarily focused on the resurfacing of US 34 (Ogden Ave.) to improve ride quality and pavement longevity, as well as the redesign and reconstruction of Americans with Disabilities Act (ADA) curb ramps. The ADA curb ramps were updated to meet current Public Right-of-Way Accessibility Guidelines (PROWAG) compliance standards, ensuring safe and accessible pedestrian crossings at intersections along the corridor. The work involved precise ramp surveying and design to ensure that all pedestrian facilities followed federal and state guidelines.
Key Elements:
- Resurfacing: Comprehensive milling and resurfacing of the roadway, improving both the structural integrity and surface smoothness of US 34. The resurfacing process also included addressing any pavement deficiencies and ensuring proper drainage along the roadway.
- ADA Curb Ramps: The redesign and construction of PROWAG-compliant ADA curb ramps at all applicable intersections, ensuring accessibility for individuals with disabilities. This included adjusting slopes, tactile warning strips, and alignment with pedestrian signals where necessary.
- Traffic Operations: Due to the heavy traffic volumes on US 34, the project employed intermittent or moving construction operations to reduce traffic disruptions and maintain flow. This approach minimized lane closures and ensured continuous mobility for both commuters and local businesses.
- Environmental Clearances and Compliance: The project required environmental clearance updates, including an Endangered Species Act (ESA) evaluation to ensure compliance with environmental regulations. Additionally, an internal sign-off was conducted to confirm the reuse of any excavated material on-site, ensuring both environmental stewardship and cost efficiency.
- Detector Loop Plans: As part of the traffic signal infrastructure, detector loop plans were provided by IDOT to ensure proper coordination between resurfacing work and the underlying signal detection systems.
Services Provided:
- Surveying and ADA Compliance Assessment: Detailed field surveys to assess the existing conditions of curb ramps and sidewalks, ensuring all ADA-related improvements met the latest regulatory requirements.
- Resurfacing and Pavement Design: Planning and designing the resurfacing strategy to extend the lifespan of US 34.
PROJECT IMPACT
Key Outcomes
Resurfaced approximately seven miles of US 34, improving ride quality and longevity
Redesigned ADA curb ramps to meet current PROWAG compliance standards
Minimized traffic disruption through intermittent and moving construction operations
Ensured accessible pedestrian crossings at all applicable intersections
Secured Endangered Species Act clearance and environmental compliance approvals
Coordinated on-site material reuse for environmental stewardship and cost savings
Aligned detector loop plans with resurfacing to maintain signal detection systems
Delivered a corridor-wide improvement enhancing safety and accessibility for all users
Project Information
Client
Illinois Department of Transportation
Location
Naperville, IL; Lisle, IL
Project Type
Resurfacing & ADA Improvements (~7 miles)
Completion
Design Completed 2017