PROJECT OVERVIEW

About This Project

The I-90/94 at I-290 Circle Interchange is located in the heart of downtown Chicago, adjacent to the west end of the central business district. Greektown is located to the northwest, and the University of Illinois at Chicago is situated to the southwest.

The Circle Interchange was built in the late 1950s and early 1960s, during the same time period as construction of the Kennedy Expressway. The Circle Interchange links to the Dan Ryan Expressway (I-90/94) to the south, the Kennedy Expressway to the north (I-90/94), the Eisenhower Expressway (I-290) to the west, and Congress Parkway to the east. Local traffic reporters commonly refer to this Interchange as the “Circle” since from above, the curving ramps appear to form concentric rings.

The Circle Interchange is critical to the nation’s transportation system, particularly for freight movement on our Interstate and arterial roadways, as well as to regional railroads and waterways. The Circle Interchange serves as a vital hub for local, regional, and national freight traffic.

The project consisted of construction inspection services for the improvement of I-90 at I-290/Congress Parkway (Jane Byrne Interchange) – I-90/94 (SB): Roosevelt Road to Lake/Madison Street. Work includes, but is not limited to, the total reconstruction of the Kennedy Expressway (I-90/94) Southbound mainline to 4 through lanes between Roosevelt Road and Lake and Madison Streets in the City of Chicago using continuously reinforced Concrete Pavement (CRCC). For the mainline lanes and Portland Cement Concrete Jointed Pavement (PCC) for the ramps and tapers, construction of one new concrete retaining wall, resurfacing the transition area at the north end of the expressway reconstruction limit in the SB direction, construction of a two-lane Collector Distributor (C-D) roadway with shoulder within the limits of the project along the west side, overhead signing, roadway lighting, ITS, drainage & pavement markings. The work also includes special waste cleanup within the Accident Investigation Site (AIS) and other areas within the project limits and construction of an underground detention storage facility underneath the AIS near the Cermak Pumping Station.

Project Information

Client

Illinois Department of Transportation (Sub to Tecma)

Location

Chicago, IL

Project Type

Construction Management & Inspection

Completion

Completed 2022

Services Provided