ISTHA - Systemwide Oasis Curb Repair Belvidere Oasis (I-90 MP 24.0) and DeKalb Oasis (I-88)
PROJECT OVERVIEW
About This Project
Systemwide Oasis Curb Repair at the DeKalb Oasis. Other work associated with the contract includes sidewalk repairs, pavement patching, drainage structure adjustments, and shoulder repairs at the parking lots for the Belvidere Oasis and DeKalb Oasis.
Work included:
- Holding a pre-construction meeting with Tollway representatives and the Contractor
- Coordination of the work with the Tollway and Oasis Management Company to minimize impacts to the public and assure accessible access was maintained at all times.
- Review and approval of construction schedule and all material submittals.
- Construction layout of all repair areas.
- Construction inspection at all times the contractor was on site to assure compliance with standards and best practices.
- Coordinated and attended periodic meeting with client and contractor.
- Material testing was provided by our material testing consultant.
- Measurement of quantities, yield checks and payment.
- Processed extra work orders, change orders and performed invoice reviews.
- Review of all material certifications.
- Pre-final and final walkthrough with appropriate personnel.
- Competed project close, as-built drawings and sent final deliverables to client.
Project Information
Client
Illinois Tollway
Location
Illinois Tollway
Project Type
Construction Management & Inspection
Completion
Completed 2018