CDOT/IDOT: US 41 from 79th St. to S. Harbor Ave. Land Acquisition

US 41 79th to Harbor Land Acquisition

PROJECT OVERVIEW

About This Project

Accurate Group, Inc. (AGI) provided critical surveying services as a subconsultant to CTE Engineers and TranSystems Corporation, ensuring the successful land acquisition and preparation for the relocation of US 41 from 79th Street to South Harbor Avenue (9200 South). AGI’s responsibilities were comprehensive and pivotal to the relocation process, including a range of technical and legal tasks, such as establishing control points, preparing detailed drawings, and ensuring precise stake-outs. Below are the details of AGI’s contributions for each project:

AGI’s Contribution to CTE Engineers:

AGI delivered all necessary surveying work to support CTE Engineers, specifically related to the land acquisition and utility management aspects of the US 41 relocation. Their responsibilities included:

  • Establishment of Control Points and Benchmarks: AGI set up essential control points and temporary benchmarks to ensure accurate and consistent measurements for the entire project. They also conducted cross-sectional surveys of the existing centerline to provide precise data for the realignment.
  • Utility Structure Mapping: Detailed drawings for all utility structures were created to facilitate the relocation effort, ensuring no conflicts or complications with existing infrastructure.
  • Legal Descriptions: AGI prepared legal descriptions for subdivided properties as well as for the acquisition of 55 parcels, providing the legal framework required for the transfer and acquisition of land rights.
  • Stakeouts and Monumentation: AGI completed the staking and setting of monuments for the 55 parcels involved in the acquisition process, as well as for the newly relocated right-of-way, ensuring accurate boundaries for the new infrastructure.

AGI’s Contribution to TranSystems Corporation:

AGI also performed a similar yet more extensive role for TranSystems Corporation on a larger portion of the same project. Their scope of work for the relocation of US 41 involved the acquisition of a higher number of parcels, requiring meticulous planning and execution:

  • Control Points and Benchmarks: AGI established the necessary control points and temporary benchmarks, again conducting cross-sectional surveys to capture precise data for the existing centerline, ensuring a smooth transition to the new alignment.
  • Detailed Utility Drawings: In conjunction with this work, AGI prepared comprehensive drawings for all utility structures to ensure accurate relocation of services and utilities.
  • Legal Documentation: The preparation of legal descriptions was a crucial aspect of AGI’s work, particularly for the acquisition of 118 parcels, which required careful attention to detail to meet all legal requirements.
  • Stakeouts and Monument: AGI staked out and set monuments for the 118 parcels, ensuring clear and precise boundaries for both the existing and the new right-of-way. They also provided monumentation for the relocated right-of-way, ensuring legal and spatial accuracy for the newly designated route.

Summary

In both instances, AGI played an essential role in the surveying and land acquisition process for the US 41 relocation. Their detailed work on control points, utility mapping, legal descriptions, and monumentation ensured that the project adhered to all legal and engineering standards. AGI’s expertise contributed significantly to the successful realignment and land acquisition required for the project, enabling a smooth transition from planning to execution.

PROJECT IMPACT

Key Outcomes

Supported land acquisition and legal documentation for 173 total parcels

Established control points and benchmarks ensuring surveying accuracy

Prepared detailed utility structure drawings avoiding relocation conflicts

Completed stakeouts and monumentation for new right-of-way boundaries

Delivered legal descriptions supporting property transfer and acquisition

Coordinated seamlessly with both CTE Engineers and TranSystems Corporation

Ensured accurate boundary data for the US 41 relocation alignment

Enabled a smooth transition from planning to construction execution

Project Information

Client

Illinois Department of Transportation / Chicago Department of Transportation (Sub to CTE Engineers and TranSystems)

Location

Chicago, IL

Project Type

Land Acquisition & Right-of-Way Surveying

Completion

Survey Completed 2015

Services Provided