PROJECT OVERVIEW

About This Project

Accurate Group, Inc. (AGI) took on a significant role in the project, overseeing the design, specifications, quantities, and construction cost estimate for the replacement of a double box culvert and filling another culvert located approximately 600 feet apart with a single triple cell box culvert. This involved intricate planning and coordination to ensure the smooth execution of the project.

In addition to the culvert replacement, AGI managed various other tasks including resurfacing, earthwork to widen the shoulders, and coordination of utilities. This comprehensive approach allowed for the project to address multiple infrastructure needs in a cohesive and efficient manner.

Navigating the regulatory landscape, AGI secured necessary permits such as the Army Corps of Engineering Section 404 Permit and IDNR Floodway Permits, demonstrating a commitment to compliance and environmental stewardship. These permits were essential in ensuring that the project met all legal requirements and environmental standards.

To minimize disruptions to traffic flow, AGI implemented staged construction and utilized a temporary traffic signal to maintain traffic flow throughout the duration of the project. This strategic approach helped to mitigate congestion and ensure the safety of motorists and construction workers.

Notably, the project was federally funded, highlighting AGI’s ability to successfully manage projects with diverse funding sources and strict compliance requirements. Through meticulous planning, attention to detail, and effective coordination, AGI successfully delivered a critical infrastructure improvement project that will benefit the community for years to come.

PROJECT IMPACT

Key Outcomes

Replaced a double box culvert with a single triple cell box culvert

Coordinated culvert consolidation across two locations 600 feet apart

Widened shoulders through targeted earthwork and resurfacing

Secured Army Corps of Engineers Section 404 and IDNR Floodway Permits

Maintained traffic flow via staged construction and a temporary signal

Successfully managed a federally funded project with strict compliance requirements

Coordinated utilities to support a cohesive infrastructure improvement

Delivered a critical infrastructure improvement benefiting the community long-term

Project Information

Client

Illinois Department of Transportation

Location

Pingree Grove, IL

Project Type

Culvert Replacement & Roadway Improvements

Completion

Design Completed 2016