PROJECT OVERVIEW

About This Project

Accurate Group, Inc. (AGI) played a critical role in the Illinois High-Speed Rail project, a $2 billion initiative aimed at upgrading and modernizing the rail infrastructure in the state. As part of the project, AGI was responsible for several key tasks that were essential to the project’s success. Specifically, AGI handled the topographic surveys and conducted turning movement traffic counts necessary for performing Intersection Design Studies (IDS) and determining Average Daily Traffic (ADT) counts at various critical intersections along the project route. These intersections included:

  • Old US Route 66 at County Highway 8
  • Broadway St. at Beaufort St.
  • University St. at Beaufort St.
  • Stripmine Rd. at IL 53
  • Main St. at IL 53
  • Mitchell St. at IL 53
  • Division St. at IL 53

Working as a sub-consultant to AECOM/URS Corporation, AGI was responsible for delivering a comprehensive range of services. These included:

  • Full topographic surveys: AGI conducted detailed topographic mapping to support the design and planning phases of the rail upgrades.
  • Land acquisition services: The company prepared plats and legal documents to facilitate the acquisition of land necessary for the project’s construction.
  • J.U.L.I.E. coordination: AGI coordinated with the Illinois Joint Utility Locating Information for Excavators (J.U.L.I.E.) to ensure the safe and accurate location of underground utilities.
  • Utility surveys: The team carried out utility surveys to map and assess the existing underground and above-ground utilities that could potentially impact the construction process.
  • Establishing horizontal and vertical controls: AGI established precise horizontal and vertical control points to ensure that the construction and alignment of the rail and related infrastructure were accurate.
  • Performing IDS and ADT counts: AGI’s traffic analysis included Intersection Design Studies and Average Daily Traffic counts to assess and plan for the impact of traffic flow at key intersections affected by the rail project.

Through these efforts, AGI contributed to ensuring the overall accuracy, safety, and efficiency of the Illinois High-Speed Rail project, supporting the seamless integration of new rail infrastructure with existing road networks and utilities.

PROJECT IMPACT

Key Outcomes

Supported a $2 billion statewide rail modernization initiative

Conducted topographic surveys across multiple critical intersections

Performed Intersection Design Studies and ADT counts along the corridor

Delivered land acquisition plats and legal documents for construction

Coordinated with J.U.L.I.E. ensuring safe underground utility location

Established precise horizontal and vertical control points for alignment

Conducted comprehensive utility surveys minimizing construction conflicts

Ensured seamless integration of new rail infrastructure with existing roadways

Project Information

Client

Illinois Department of Transportation (Sub to AECOM)

Location

Chicago, IL to St. Louis, MO

Project Type

High-Speed Rail Corridor Survey & Traffic Analysis

Completion

Survey Completed 2016